W. W. & F. Museum Events of January, February and March, 2013

Locomotive 9: Running gear work was in full stride during the quarter. By the end of the quarter, the engine had received its driving wheels, but the decision was made to leave it in the air for ease of access.

Restrooms: Gas heaters were installed, and electricity and plumbing was run. Blown-in insulation in the ceiling was put in. The sheetrock was mudded and painted. Tiles were purchased for soon installation.