W. W. & F. Museum Events of January, February and March, 2012

Locomotive 9: During the quarter, the work to tie the cylinder saddle to the frame was completed. Work started to attach parts and pieces to the frame. The rear frame was flipped, and moved over to Bay 1 behind the boiler. The forward frame was flipped on its side and more parts were attached. Toward the end of March the boiler was raised up and the rear frame was put in around the firebox.

Creamery Car: Car 65's frame and box was constructed, with interior and exterior siding, two windows, and roof built, couplers installed, and shop trucks were put under it. Painting began as well.